Week 23

Task Action Person Responsible Complete
Complete Audio Loading and Saving Program Jason Complete
Update HuD Design Draw and submit Ali Complete
Design Menu Background Draw and Submit Reece Complete

As mentioned in the previous meeting the team are unable to make easy contact and have in depth discussions on the project and therefore the work is kept lighter to be ready for the retune to correct the issues.

Task Action Person Responsible Complete
Program HUD and Menu Program Jason 09/04/17
Additional Sprites Draw and submit Ali 13/04/17
Complete Menu Background Draw and Submit Reece 09/04/17

Due to the issues with direct communications between teammates during the separation for the remaining week, work to fix issues such as HuD and menu concepts is difficult to discuss and explain, for now the resources will be made and will be tested to make sure they are ready for when the team return to fully work on the section.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s